A number of works slated to be accomplished in 2020 have been delayed at Gurugram, primarily on account of restrictions on development actions and the unavailability of labor because of the ongoing pandemic.

Hit by the COVID-19 outbreak final yr, initiatives to enhance numerous hubs within the Millennium Metropolis together with Atul Kataria Chowk and HUDA Metropolis Heart Chowk, enlargement of a bit of the Gurugram-Alwar (NH-248A) and Patadui Street freeway, have been delayed for a number of months now.

Scheduled for completion in 2020, the Atul Katariya Chowk and HUDA Metropolis Heart Chowk initiatives, involving the development of an overflight and an underpass every, have now been primarily delayed. on account of restrictions on development actions and the unavailability of labor because of the pandemic since March of final yr.

Initially, which was on account of be accomplished by December four, 2019, the Atul Katariya Chowk Junction Renovation Challenge, a challenge introduced by Chief Minister Manohar Lal, was anticipated to be accomplished by the top of 2020 .

Shifting utilities

The delay was primarily because of the relocation of utilities. Nonetheless, a gathering of the Gurugram Metropolitan Improvement Authority (GMDA) in December final yr to evaluation numerous initiatives discovered that solely 27% of the work had been accomplished and prolonged the date for ; challenge completion till February 2021.

The tender for the challenge was awarded on Might 5, 2018, at a value of ₹ 47.70 crore and consists of the development of a 715 meter lengthy flyover alongside Previous Delhi Street and a 620 meter lengthy underground passage alongside the Mata highway, along with a service highway.

Likewise, the HUDA Metropolis Heart Chowk Enchancment Challenge consists of the development of a 270-meter-long flyover and a 735-meter-long underpass from Signature Street to Subhash Chowk. Over 80% of the overflight work has been accomplished, however the progress of the civil works achieved is barely 41%.

The completion date of the works has now been prolonged to March 2021. The works for the challenge have been awarded on February 25, 2019, at a value of ₹ 52.52 crore and the date is ₹ 52.52 crore. scheduled completion was April 15, 2020.

Properly not on time, the junction enchancment challenge at Mahabir Chowk and Aggarsen Chowk close to the town bus cease was awarded on February 15, 2019 and in keeping with the contract the works have been on account of be accomplished by December 14, 2020, at a value of ₹ 25.92 crore.

Nonetheless, the challenge has solely progressed by 12% and is anticipated to be delayed. The works are undertaken by the general public works division (buildings and roads) with funds offered by the GMDA.

Deadline handed

Scheduled to be accomplished by Might 11, 2020, as per the contract, the Umang Bhardwaj Chowk six-lane highway challenge to Dwark Expressway has seen an total progress of 36% and on date. completion has now been prolonged till March of this yr. .

It includes an 820-meter-long overflight at Basai Chowk and a 910-meter-long railway over the bridge (ROB) on the Delhi-Rewari railway line. ORB's constructing permission has been acquired and most points associated to the switch of utilities and land disputes have been resolved.

Forward of schedule, the four-lane underground U-turn close to Atmosphere Mall, a challenge of the Nationwide Highways Authority of India (NHAI), is anticipated to be accomplished on Might 31 of final yr. However the challenge has now been delayed past its September 2020 deadline, per contract, because of the COVID-induced lockdown and shortage of funds.

NHAI was to bear half of the price of the ₹ 102.94 crore challenge, with the remainder to be shared equally by the DLF and the homeowners of the Atmosphere mall. However the homeowners of DLF and Atmosphere Mall have delayed funds. "The DLF has now paid its share and the challenge is anticipated to be accomplished by March of this yr," mentioned a senior NHAI official.

Journey time

Motorists coming from Jaipur and heading to Atmosphere Mall and DLF Cyber ​​Hub are actually compelled to drive as much as Rajokri flyover in Delhi to show round. When accomplished, the 377-meter-long underground U-turn is not going to solely scale back journey time, but additionally assist scale back visitors congestion underneath the Rajokri Bridge throughout rush hour.

For the six-lane development and reinforcement of the 22 km lengthy part of the nationwide highway 248A, identified domestically as 'Sohna Street', from Rajiv Chowk, the NHAI awarded two tenders distinct. The primary package deal of the challenge consists of six lanes and the strengthening of the highway from zero.340 km to 9.282 km from Rajiv Chowk and an elevated highway four.752 km lengthy. The scheduled date for the completion of this package deal, as per the contract, is July 31, 2021. The second package deal, with a completion date of July 29, 2021, covers the remaining distance.

A 3-lane service highway may even be constructed on each side of the highway.

“The 2 packages of the challenge are in progress. The primary package deal, with 32% progress, is anticipated to be accomplished by June of subsequent yr. Nonetheless, the second package deal is about 70% full and we hope to finish it by the top of the yr, ”the NHAI official mentioned, unwilling to be named.

Apart from the pandemic, the primary package deal of the challenge was additionally delayed because of the collapse of a bit of an elevated hall in August of final yr.